Zaporizhzhia region’s public investment ceiling for 2026 is UAH 225.8 million. Yet the 14 projects competing for priority funding from the regional budget have a combined price tag of nearly UAH 1.1 billion. They range from science parks and the university’s “smart shelters” to an interactive map and two similarly named video surveillance projects.
These are the findings of monitoring conducted by the NGO “Narodnyi Zakhyst” as part of the Public Investment Watchdog project. The monitoring examined how the frontline region and its regional capital are implementing the public investment management (PIM) reform. The main problem, it turned out, is not the figures themselves, but the fact that they have to be pieced together from multiple sources.
Reform behind closed doors
At the start of the monitoring process, experts sent information requests to the Zaporizhzhia, Vinnytsia and Dnipropetrovsk Regional Military Administrations (RMAs), as well as the Kyiv City State Administration (KCSA), asking for a list of public investment projects (PIPs) for 2026. None of the authorities provided even a partial list.
The official website of the Zaporizhzhia Regional State Administration has no dedicated section on the reform. The only mention is a news item about training on how to use the DREAM system. As a result, the research had to rely on orders issued by Ivan Fedorov, Head of the Regional Military Administration, which were themselves published only in fragments.
The Local Investment Council was established by Order No. 779 of 21 July 2025, but the document itself has not been made public. The council’s membership was subsequently amended twice, in August and November 2025. It is chaired by Ivan Fedorov and includes no civil society representatives or independent experts. No meeting minutes could be found in the public domain.
The Medium-Term Plan for Priority Public Investments (MTPI) for 2026–2028 was approved by Order No. 919, dated 1 September 2025. Responsibility for overseeing its implementation was assigned to Ivan Fedorov himself. Like the other regions covered by the monitoring, Zaporizhzhia has no regional roadmap for implementing the reform. Its documents refer only to the national government’s action plan.
A plan for 2028 without a strategy for 2028
The logic of the reform is straightforward: first, a strategy sets out the vision; then the Medium-Term Plan for Priority Public Investments (MTPI) translates it into management decisions – what to fund first, what to phase in, and where to seek external funding. In Zaporizhzhia region, this chain is broken. The MTPI runs through 2028, while the Regional Development Strategy covers only the period up to 2027. In other words, priorities for 2028 have been set without approved strategic objectives for that year.
Zaporizhzhia region has selected 15 priority sectors – the highest number among the regions covered by the monitoring. By comparison, Vinnytsia region has identified seven sectors and Kyiv ten. When almost everything is declared a priority, there is effectively no real management choice.
The total ceiling for public investment over the three-year period is UAH 857.7 million: UAH 225.8 million in 2026, UAH 246.8 million in 2027 and UAH 385 million in 2028. The largest allocations are planned for education and science (UAH 120 million), healthcare (UAH 111.8 million) and municipal infrastructure (UAH 110 million). By contrast, mine action in this frontline region is allocated just UAH 1 million per year – the same amount as for the agricultural sector and economic activity.
Going underground until 2029
The most revealing figures in the MTPI are the targets set for the “Education and Science” sector. They indicate that the regional authorities expect the security threat to persist at least through the end of 2028.
| Target indicator |
Baseline |
2028 target |
| Underground schools |
25 |
55 |
| Underground kindergartens |
0 |
12 |
| Underground universities |
0 |
1 |
| Buses purchased (including those for children with disabilities) |
96 |
156 |
| Canteens and school kitchens built or modernised |
2 |
12 |
The rationale is understandable: the regional capital lies close to the frontline and is regularly subjected to shelling. However, these targets should be supported by estimates of how many children are expected to attend these facilities and an explanation of how the plans fit into the region’s development strategy beyond 2027. No such justification can be found in the publicly available documents.
Who is in line for regional funding?
The broad range of priority sectors has allowed very different projects to compete for priority funding from the regional budget in 2026. All but the park reconstruction project are classified as investment feasibility studies (investment FS).
| Project |
Service users |
Cost, UAH million |
| Science Park of Zaporizhzhia National University (ZNU) |
1,000 |
220.0 |
| Network of veterans’ spaces |
70,000 |
178.7 |
| Video surveillance and analytics system for Zaporizhzhia |
11,456 |
146.2 |
| Reconstruction of Metallurgists’ Park named after V. A. Satsky (preliminary FS) |
20,000 |
131.0 |
| Integrated video analytics system for Zaporizhzhia |
Not specified |
111.9 |
| ZNU Centre for the Restoration and Preservation of Historical Heritage |
1,000 |
100.0 |
| ZNU Smart Shelter |
1,000 |
100.0 |
| Regional Centre for the Digital Transformation of Enterprises and Institutions |
1,000 |
38.0 |
| Reconstruction of beach volleyball courts |
5,000 |
23.2 |
| Composting site |
20,000 |
16.8 |
| Park of Honour Memorial Complex on Khortytsia Island |
3,000 |
14.1 |
| Equipment for the Regional Centre for National Resistance and Veterans Policy |
3,500 |
5.0 |
| Regional AI Centre |
1,000 |
2.0 |
| Interactive Map of the Region’s Resilience and Cohesion |
10,000 |
0.7 |
The three ZNU projects alone have a combined cost of UAH 420 million – almost twice the region’s entire public investment ceiling for 2026. Five projects list exactly the same number of service users – 1,000 – while one does not provide a figure at all. This looks less like a meaningful estimate and more like a box-ticking exercise.
Experts from Narodnyi Zakhyst note that some of these projects were previously registered as reconstruction projects. Others are essentially routine capital expenditure or procurement of goods and do not qualify as public investment projects under the reform.
One park, two budgets
The reconstruction of Metallurgists’ Park named after V. A. Satsky is seeking UAH 131 million from the regional budget. Yet the same project is also being considered for UAH 100.2 million in funding from the Zaporizhzhia city budget, with municipal enterprise “Titan” listed as the initiator. Both applications cite the same number of intended service users: 20,000.
According to the monitoring findings, this amounts to potential double funding for a single site, totalling more than UAH 231 million. The reform was designed precisely to prevent such situations. Under its approach, communities should fund their own projects first, with regional funding added only when a project also contributes to broader regional development goals. In this case, however, neither the division of costs between the two budgets nor the rationale for regional funding is clear.
Similar concerns arise over two video surveillance projects in Zaporizhzhia, with budgets of UAH 146.2 million and UAH 111.9 million. Their titles are almost identical, yet the publicly available documents provide no way to determine whether their scope overlaps.
The city: 156 projects, but almost none funded
At the city level, Zaporizhzhia offers a more transparent picture: the Unified Project Portfolio is publicly available, and the city council responded to the monitoring team’s information request. The portfolio lists 156 projects across 11 sectors, with the latest amendments made in May 2026. All are still at the stage of developing an investment or preliminary feasibility study.
The community’s priorities reflect the realities of war. More than half of all projects – 90, or 57.7% – concern municipal infrastructure, including cogeneration units, water supply and wastewater facilities, heating networks and protective structures. Another 43 projects relate to education, most of them involving the construction of radiation shelters in schools and kindergartens. Housing accounts for 17 projects focused on restoring buildings damaged by shelling, while 16 healthcare projects involve hospital renovations and the procurement of CT scanners, MRI machines and angiography systems. Some projects are assigned to more than one sector, which is why the combined shares exceed 100%.
The main project initiators are the relevant city council departments and municipal enterprises, including the Departments of Education and Science, Housing and Municipal Services, and Healthcare, as well as the municipal enterprise Capital Construction Management. According to the monitoring findings, the heads of these departments and enterprises have no influence over project approval or funding priorities.
The education sector, which accounts for the largest number of shelter projects, also raises sensitive questions. In August 2025, Vitalii Lysenko, then acting Director of the Department of Education and Science, was notified of suspicion of misappropriating more than UAH 8.6 million in connection with the procurement of backup power systems for schools. In October 2025, an appellate court suspended him from office for two months, according to Suspilne. The official has not been found guilty by a court.
The city authorities themselves point to three key challenges:
- Security takes priority over economic considerations. In project assessments, shelters and housing reconstruction were consistently given top priority, while economic viability criteria were often marked as “not applicable”.
- Limited funding. The community’s budget is constrained by martial law, leaving most feasibility studies dependent on state subsidies or international assistance.
- A shortage of qualified specialists. Schools and hospitals lack in-house expertise to assess climate impacts, apply the DNSH principle or analyse the contractor market. As a result, project portfolio entries often contain template responses rather than in-depth analysis.
The overall picture is discouraging: most of the city’s projects currently have no identified source of funding.
What needs to change
Zaporizhzhia is a frontline region, where the priority given to security is beyond question. Yet when resources are scarce, the consequences of poor decisions are particularly serious. The public investment management (PIM) reform is designed precisely to ensure that funding goes to projects that genuinely address local needs – and that the decisions behind those allocations are open to scrutiny.
So far, however, the reform in the region has been largely a formality. Decisions rest with a single person, the Local Investment Council operates without public participation or published minutes, and the value of projects competing for funding is five times the available budget. At least three steps are needed to change this: publish the reform documents and the council’s minutes; involve independent experts and civil society representatives in its work; and reconcile the regional and municipal project portfolios to prevent the same project from being funded twice.
The next test for the region will be the new strategic planning cycle after 2027. Whether this process is open and transparent will determine whether the medium-term plan becomes a genuine tool for setting priorities and making informed investment decisions.
This article was prepared as part of the Public Investment Watchdog project, implemented by the Institute for Economic Research and Policy Consulting (IER), the Centre for Economic Strategy and NGO “Technology of Progress”, with the support of the European Union.